The construction of the astro-turf pitch is progessing well. The site is now cleared, the first layer of stone is in place and the drainage work is completed. The pads are now in place for Hurling Wall.
The next steps are:
- Hurling wall to be delivered and erected in next 1-2 weeks.
- Next stage is then fencing and kerbing.
- After that is the laying of final stone, levelling of same and laying of grass surface.